Practice Examination — Set 1
For BBS · Fourth Year
Based on the prescribed TU Faculty of Management syllabus and examination structure
Candidates are required to give their answers in their own words as far as practicable. The figures in the margin indicate full marks.
Group 'A'
Brief Answer Questions. Attempt ALL questions.
[10 × 2 = 20]- [2]
Define a ‘Project’ and state its 3 core constraints (Triple Constraint).
View model answerHide model answer
Project: A temporary endeavor undertaken to create a unique product, service, or result. Triple Constraint: Scope, Time, and Cost (Quality at the center).
- [2]
What is a ‘Work Breakdown Structure’ (WBS)?
View model answerHide model answer
Concept: A hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and deliver required deliverables.
- [2]
Define ‘Critical Path’ in project scheduling.
View model answerHide model answer
Concept: The longest sequence of dependent activities through a project network diagram which determines the shortest possible duration to complete the project. Float on the critical path is zero.
- [2]
Differentiate between CPM and PERT.
View model answerHide model answer
Distinction:
- CPM (Critical Path Method): Deterministic model with known, fixed activity durations (common in construction).
- PERT (Program Evaluation & Review Technique): Probabilistic model using 3 time estimates (Optimistic, Most Likely, Pessimistic) for uncertain research/development projects.
- [2]
What is ‘Float’ (Slack) of an activity?
View model answerHide model answer
It represents the amount of time an activity can be delayed without delaying the project completion date.
- [2]
What is ‘Earned Value Management’ (EVM)?
View model answerHide model answer
Concept: A project monitoring methodology that integrates project scope, cost, and schedule metrics to assess project performance and progress against the baseline.
- [2]
Define ‘Cost Performance Index’ (CPI).
View model answerHide model answer
If
, the project is performing under budget (efficient); if , the project is over budget. - [2]
What is ‘Project Crashing’?
View model answerHide model answer
Concept: A schedule compression technique in which extra resources are added to critical path activities to shorten overall project duration at the lowest additional cost.
- [2]
Define ‘Scope Creep’.
View model answerHide model answer
Concept: The uncontrolled expansion of project scope without adjustments to time, cost, and resources, usually leading to project failure.
- [2]
What is a ‘Project Post-Implementation Review’ (Post-Mortem)?
View model answerHide model answer
Concept: A formal evaluation conducted after project handover to assess whether intended business benefits were achieved and document lessons learned for future projects.
Group 'B'
Short Answer / Descriptive Questions. Attempt any FIVE questions.
[5 × 10 = 50]- [10]
Explain the 5 Project Management Process Groups per the PMBOK guide.
View model answerHide model answer
1. Initiating: Defining project charter, business case, and identifying stakeholders. 2. Planning: Establishing total scope, defining WBS, schedule network, budget, quality standards, and risk register. 3. Executing: Coordinating project teams, procuring equipment, and building deliverables. 4. Monitoring and Controlling: Tracking progress, managing scope changes, analyzing EVM variances, quality audits. 5. Closing: Formal deliverable acceptance, contract closeout, financial settlement, and archiving lessons learned.
- [10]
A project activity has: Optimistic Time (
) = 4 days, Most Likely Time ( ) = 7 days, Pessimistic Time ( ) = 16 days. Calculate: (a) Expected Time ( ), (b) Variance ( ), and (c) Standard Deviation ( ). View model answerHide model answer
Step 1: Expected Time (
): Step 2: Standard Deviation (
): Step 3: Variance (
): - [10]
Explain Earned Value Management (EVM) metrics: Planned Value (PV), Earned Value (EV), Actual Cost (AC), Cost Variance (CV), and Schedule Variance (SV).
View model answerHide model answer
EVM Metrics:
- Planned Value (PV): Authorized budget assigned to scheduled work.
- Earned Value (EV): Value of work actually performed expressed in terms of approved budget.
- Actual Cost (AC): Real cost incurred for work performed.
- Cost Variance (CV):
(Positive = under budget, Negative = over budget). - Schedule Variance (SV):
(Positive = ahead of schedule, Negative = delayed). - Schedule Performance Index (SPI):
.
- [10]
Discuss the Project Risk Management Process (Risk Identification, Qualitative/Quantitative Assessment, and Risk Response Strategies).
View model answerHide model answer
Risk Management Steps:
- Identification: Brainstorming, Delphi technique, checklist analysis.
- Qualitative Risk Analysis: Prioritizing risks by Probability and Impact rating.
- Quantitative Risk Analysis: Expected Monetary Value (EMV), Monte Carlo simulation.
- Risk Response Strategies:
- Negative Risks: Avoid, Mitigate, Transfer (insurance/subcontracting), Accept.
- Positive Risks (Opportunities): Exploit, Share, Enhance, Accept.
- [10]
Explain the role and responsibilities of an effective Project Manager.
View model answerHide model answer
Key Responsibilities:
- Leading cross-functional project teams and resolving interpersonal conflict.
- Managing stakeholder expectations and scope change requests.
- Ensuring project delivery on time, within budget, and meeting quality standards.
- Proactive risk identification and crisis management.
- Transparent status reporting to project steering committee.
- [10]
Discuss the major causes of Project Cost and Time Overruns in public infrastructure projects in Nepal.
View model answerHide model answer
Causes of Delays in Nepal:
- Land acquisition and right-of-way disputes.
- Inadequate detailed engineering design and frequent mid-stream design changes.
- Bureaucratic delays in environmental impact assessment (EIA) and tree-cutting approvals.
- Public procurement disputes and low-bidding by contractors leading to abandoned sites.
- Geographical landslides, terrain difficulties, and seasonal monsoon interruptions.
Group 'C'
Comprehensive / Analytical Questions. Attempt any TWO questions.
[2 × 15 = 30]- [15]
The following network data is given for a construction project:
- Activity A (1-2): Duration 4 days
- Activity B (1-3): Duration 6 days
- Activity C (2-4): Duration 5 days
- Activity D (3-4): Duration 3 days
- Activity E (4-5): Duration 7 days Draw the network diagram, identify all paths, determine the Critical Path and Total Project Duration, and calculate Earliest/Latest times and Float for all activities.
View model answerHide model answer
Step 1: Identify Network Paths:
- Path 1:
(Activities A C E) - Duration =
.
- Duration =
- Path 2:
(Activities B D E) - Duration =
.
- Duration =
Step 2: Critical Path & Project Duration: Both Path 1 and Path 2 have equal maximum duration of 16 days. Hence, both paths are Critical Paths:
- Critical Path 1: A – C – E (16 days)
- Critical Path 2: B – D – E (16 days)
- Total Project Duration: 16 Days.
Step 3: Earliest and Latest Times Table:
Activity Duration ES EF LS LF Total Float (LS - ES) Status A (1-2) 4 0 4 0 4 Critical B (1-3) 6 0 6 0 6 Critical C (2-4) 5 4 9 4 9 Critical D (3-4) 3 6 9 6 9 Critical E (4-5) 7 9 16 9 16 Critical Conclusion: All activities have zero float; any delay in any activity will delay the entire project.
- [15]
Explain Earned Value Analysis with a numerical problem. At Day 50 of a project, the following information is available:
- Planned Value (PV) = Rs. 500,000
- Earned Value (EV) = Rs. 420,000
- Actual Cost (AC) = Rs. 480,000
- Total Budget at Completion (BAC) = Rs. 1,000,000 Calculate: (a) Cost Variance (CV), (b) Schedule Variance (SV), (c) Cost Performance Index (CPI), (d) Schedule Performance Index (SPI), and (e) Estimate at Completion (EAC). Interpret project health.
View model answerHide model answer
Step-by-Step Calculations:
- Cost Variance (CV):
- Schedule Variance (SV):
- Cost Performance Index (CPI):
(For every rupee spent, only 87.5 paisa worth of work was completed).
- Schedule Performance Index (SPI):
(Project is progressing at only 84% of scheduled rate).
- Estimate at Completion (EAC):
Project Health Interpretation: The project is in critical condition: it is running behind schedule by Rs. 80,000 and over budget by Rs. 60,000. If current efficiency continues, total cost will overrun by Rs. 142,857 over the original Rs. 10 Lakh budget.
- [15]
Examine Project Management in Nepal. Discuss the institutional role of the National Planning Commission (NPC) and project monitoring frameworks for National Pride Projects (e.g. Upper Tamakoshi, Pokhara Airport, Fast Track). What institutional reforms are needed?
View model answerHide model answer
1. National Planning Commission (NPC) Role: Formulates national periodic plans, establishes project appraisal guidelines, and conducts central project monitoring and evaluation (M&E).
2. Status of National Pride Projects:
- High capital commitments with immense economic transformation potential (hydropower, highways, airports).
- Chronic delays: Time overruns of 5–10 years and cost escalations exceeding 100% due to geological surprises, poor contractor accountability, and political instability.
3. Required Institutional Reforms:
- Transition from lowest-bid (L1) tender awards to Quality and Cost Based Selection (QCBS).
- Fast-track land compensation dispute tribunals.
- Enforcement of strict liquidated damages on defaulting contractors.
- Depoliticization of Project Directors with fixed performance-based tenures.